Basics of Correspondence

Basics of Correspondence

Purpose:

To Create a Correspondence.

Background:

In Contractor Foreman, Correspondence is broken down into three categories.

Points to Remember:

Required fields are marked with an Asterisk (*.) To save your work, click the blue Submit button. To edit the record, click the green pencil icon in the upper right corner. Deleting Items can only be done by a person with Admin Rights or if you are given access to do so. If a Correspondence need to be Deleted, you can do so by clicking on the Action button at the bottom of the page on the right.

Steps to Create a New Correspondence:

  1. Navigate to Main Menu.
  2. Click on Correspondence
  3. Click on blue button Create a New Schedule Notice Create a New Compliance Notice Create a New RFI (Request for Information) on the left.
  4. Enterthe followinginformation:

Create a New Schedule Notice:

  • Project: (Mandatory) Select from System List.
  • To: (Mandatory) Select from System List.
  • From: Select from Drop-down.
  • Date/Time:
  • Items #: Save to View.
  • Notice Type: (Mandatory) Select from Drop-down.
  • # Of Days Delayed:
  • Notes:

Create a New Compliance Notice:

  • Compliance Type: (Mandatory) Select from Drop-down.
  • Project: (Mandatory) Select from System List.
  • Date/Time: (Mandatory)
  • To: (Mandatory) Select from System List.
  • From: Select from Drop-down.
  • Item #: Save to View.
  • Description of Issue:
  • Resolution Date:
  • Resolution or Response:
  • Status:
  • Add an Attachment: Upload all Photos & Files in link to this Project. (On the phone or Tab this would be a Camera button so just click away & it will upload here automatically)

Create a New RFI (Request for Information):

  • Project: (Mandatory) Select from System List.
  • Date/Time: (Mandatory)
  • To: (Mandatory) Select from System List.
  • From: Select from Drop-down.
  • Item #: Save to View.
  • Information Requested: (Mandatory)
  • Referenced Area in Question:
  • Change Order: Select from Drop-down.
  • Plan Sheet Number:
  • Response Needed By:
  • Response Received:
  • Response:
  • Status:
  • Add an Attachment: Upload all Photos & Files in link to this Project. (On the phone or Tab this would be a Camera button so just click away & it will upload here automatically)
    • Related Articles

    • Basics of Reports

      Purpose: To easily and quickly get you the data you need to help you run your business.. Background: Within Contractor Foreman there are multiple pre-built reports for you to use. And we are adding more all the time. Points to Remember: All Reports ...
    • Correspondence Overview

      Correspondence In Contractor Foreman, Correspondence is broken down into three categories. Schedule Notices: This is for when an owner or subcontractor or vendor has or is causing a schedule delay to the project, as well as regular Schedule updates ...
    • Basics of Change Orders

      Purpose: To Create a Change Order. Background: In Contractor Foreman, Change Orders are used to document and track any changes that were made to the original contract amount. You have the ability to track who requested and who approved as well as ...
    • Basics of Company Settings

      Purpose: To setup your company information and assign defaults and tweaks to get the most out of your account. Background: Use these setting to designate your Currency, Date and Number format. Add your local state and any other tax you need to ...
    • Basics of Directory

      Purpose: To Create a Directory. Background: Contractor Foreman breaks down your contacts into categories. These help with organization as well as speeding up data entry by keeping lists shorter and searches faster. The categories are, Employees, ...