How do I add a Crew for use with the Crew Schedule or Timecards?

How do I add a Crew for use with the Crew Schedule or Timecards?

To add a Crew, go to the Menu and select Settings. In here, scroll down and choose Crew Schedule. Scroll down to Crews and then click the Add Crew button and start adding crew members to the new crew.
    • Related Articles

    • Timecards

      Timecards In Contractor Foreman, you have the option of turning on or turning off GPS Tracking (See Settings). If turned on, GPS tracking only logs the current location of where an employee clocked in at and clocked out at. It does not track all ...
    • How do I create or edit a crew?

      Select CREW SCHEDULE from Menu. Press the "Settings" Gear in the upper right corner of the display. Add a CREW by pressing the Add Crew button and choose the Crew Leader and Crew Members from the available lists of Employees and Contractors. Make ...
    • How to add an item on the Schedule of Values?

      Adding an item to SOV can be done in multiple ways. The best & quickest way is to Import. You can Import from an Estimate, Change Order or Work Order. You can also add an item Manually if the item is not in your database. To add items to SOV go to: ...
    • How do I notify my crew about their work schedule?

      You have two options. You can press the SEND SCHEDULE button in the upper right corner of the screen when you have the CREW SCHEDULE open. Or, you can individually send out a notification to a single crew member by clicking on the "BullHorn" icon ...
    • Can I show my project schedule (Gantt items) on my Crew Schedule?

      It isn't possible to show Project schedule on Crew Schedule. These are currently 2 different types of schedules, one of planning (Gantt) and one for resource scheduling (Crew Schedule). You can however display the Gantt Schedule tasks as well as the ...