How do I create a Gantt chart for any project and track that project?

How do I create a Gantt chart for any project and track that project?

You can let the Estimate create the Schedule for you based off the line items in the Estimate (Watch Estimating Video) and you can also create the CPM/Gantt Chart Schedule Manually by first adding start and finish dates in the Project Detail screen, clicking save. Then going to Schedule module and adding the tasks manually. You can also import Schedules from MS Project and Copy and existing Schedule. To do this select either option under the "Action" drop down in upper right hand corner of screen.